Well No. 11B Drilling Project

This project is the first step of constructing a new well at the Wastewater Treatment Resource Recovery Facility.
The project includes:
- Drilling and providing for a 24-inch surface casing to a 25-foot depth
- Drilling and providing for a 20-inch casing to a 260-foot depth
- Providing for the 20-inch casing to extend above surface level to a height of 2-feet
- Drilling the remaining 18-inch lower hole to a 400-foot depth
- Providing for an intermediate flow test
- Providing for well development and a pump test of up to 2,400 gallons per minute.
Drilling is one phase of the overall project. City plans to bid a Well House Construction Project in winter2023; with bidding dependent on the drilling phase. The City also plans to pre-purchase motor, discharge head, and bowls based on the pump test results while the well house is under construction.
- Well 11B Wellhouse Project: At 90% and has been reviewed by State of Oregon. To be advertised in January / February 2023.
- Well 11B Pumping Equipment: To be solicited after the well is drilled and the pump test performed, tentatively scheduled for late-winter to early-spring.
Funding
This project is being funded through the Federal Safe Drinking Water Revolving Loan Fund, Business Oregon, and local funding.
| Project Title: | Well No. 11B Drilling Project |
| Estimated Construction Cost: | $950,000 |
| Actual Construction Cost: | $782,023 |
| Project Type: | Water |
| Final Project Cost (Construction + Engineering): | TBD |
| Year Completed: | In Progress |
Address
4255 SW 28th Dr, Pendleton, OR 97801, USA
Additional Links:
Project Status
In Progress
Project Milestones
November 2022
Bid/RFP Due Date
November 2022
Bid award for Drilling to Holt Services, Milton, WA, in the amount of $782,023.