Til Taylor Park Rebuild

The Til Taylor 101 Project, named for its completion on the 101st anniversary of Sheriff Til Taylor’s murder, revitalized one of Pendleton’s most historic parks.

Project included:

  • Two new playgrounds
  • Splash pad to replace deteriorating wading pool
  • Fenced-in dog park 
Project Title:Til Taylor 101 Park Rebuild Project
Estimated Construction Cost:TBD
Actual Construction Cost:TBD
Project Type:Parks
Final Project Cost (Construction + Engineering):TBD
Year Completed:2022

Why It's Needed
Revitalizes one of Pendleton's parks and provides a safe and ADA accessible water feature for families.  

Address

Additional Links:

Til Taylor 101 Park Rebuild Project

Project Status

Completed

Project Milestones

March 2021

Bid awarded to 2KG Contractors Inc

 

August 2021

Splash Pad opens to the public

 

July 2022

Dog Park opens to the public