The Til Taylor 101 Project, named for its completion on the 101st anniversary of Sheriff Til Taylor’s murder, revitalized one of Pendleton’s most historic parks.
Project included:
- Two new playgrounds
- Splash pad to replace deteriorating wading pool
- Fenced-in dog park
| Project Title: | Til Taylor 101 Park Rebuild Project |
| Estimated Construction Cost: | TBD |
| Actual Construction Cost: | TBD |
| Project Type: | Parks |
| Final Project Cost (Construction + Engineering): | TBD |
| Year Completed: | 2022 |
Why It's Needed
Revitalizes one of Pendleton's parks and provides a safe and ADA accessible water feature for families.
Address
Additional Links:
Project Status
Completed
Project Milestones
March 2021
Bid awarded to 2KG Contractors Inc
August 2021
Splash Pad opens to the public
July 2022
Dog Park opens to the public