SW Tutuilla Road Sewer Line Project

This project installs a 12” sanitary sewer main approximately 273 feet in length under Tutuilla Creek to Tutuilla Road and approximately 1,096 feet of 8” sanitary sewer pipe in Tutuilla Road up to SW Runnion Avenue. 

The project also includes: 

  • Connecting into an existing manhole by coring the existing manhole at Station 0+00 that presently has a 12” sanitary sewer line running through it adjacent to Tutuilla Creek
  • Constructing a new 12”, 3034 PVC pipe through a new manhole
  • Installation of an outside drop manhole and two separate 8” lines are to be installed, one to the east right-of-way line or Tutuilla Road at approximately 12 feet deep, and one continuing south on Tutuilla Road at a depth between 6 and 7 feet deep
  • Two 8” lines and one 6” line will be stubbed out to the east right-of-way of Tutuilla Road for future extension
  • Three 4” service laterals will be stubbed out to adjacent parcels lying on the west side of Tutuilla Road
  • Replacement of some curb, gutter, and sidewalk/driveway approaches as needed to install new service laterals and stub-outs for future extension

See an overview video of the project at this link.

Project Title:SW Tutuilla Road Sewer Line Project
Estimated Construction Cost:$364,000.00
Actual Construction Cost:TBD
Project Type:Wastewater
Final Project Cost (Construction + Engineering):TBD
Year Completed:2023

Why It's Needed
This project extends wastewater service into property slated for future development.  

Address
SW Nye Ave & Tutuilla Rd, Pendleton, OR 97801, USA

Additional Links:

SW Tutuilla Road Sewer Line Project Documents

Project Status

Completed

Project Milestones

October 2022

City of Pendleton Public Works crews completed phase one of the project: installing 38-feet of this sewer pipe under the creek  to meet the requirements of a DEQ permit. The creek was dry at the time, and the work was done in just a few days.

 

January 2023

SW Tutuilla Road Sewer Line construction project bid be awarded to Precision Paving Plus, LLC, of Woodland, Washington., for $276,407.75

 

March 2023

Road work begins on project, causing single-lane closures.

 

July 2023

Project completed