Solar Panels at WWTRRF

Project will cover the Chlorine Contact Chamber at the Wastewater Treatment Resource Recovery Facility (WWTRRF) with solar panels. The solar array shading is designed to reduce facility power costs by integrating a renewable resource, providing at least 240-300 kilowatt hours of power.

Additionally, placing the panels over the chlorine contact chamber provides shade to cool the water and reduce the amount of chlorine chemical lost due to UV degradation.  The City of Pendleton expects to see long-term cost savings when the solar array is completed, and city staff is also pursuing Energy Trust of Oregon funding to make up part of the city match amount.

Funding

The City of Pendleton will fund the project through sewer capital reserve funds and will be reimbursed through an $813,000 Construction Resilience grant from Oregon Department of Energy (ODOE) through the Community Renewable Energy Program (CREP) for this project to support community energy resilience, $488,000 in Federal Investment Tax Credit funds, and funding from the Energy Trust of Oregon ($19,800).  The remaining amount ($530,000) will be funded through the sewer fund.

Project Title:WWTRRF Chlorine Contact Chamber Solar Panels
Estimated Construction Cost:$1,855,100
Actual Construction Cost:TBD
Project Type:Wastewater
Final Project Cost (Construction + Engineering):TBD
Year Completed:2025

Why It's Needed
Covering of the CCC will provide three key benefits: first being the production of power for the facility, second is the shading of the chamber reducing the amount of chlorine chemical lost due to UV degradation, third is the cooling effects from the shading on the water. The addition of covering the secondary clarifier will also provide similar benefits minus the reduction in chlorine usage. Each year, the WWTRRF spends about $120,000 in power bills, and this project is expected to reduce that amount by a third ($40,000) each year in addition to the savings in purchase of chlorine. This is part of a long-term facility goal to become energy self-sustaining. There are four primary benefits for the solar array covering the Chlorine Contact Chamber (CCC) with a solar panel array: 1. Electricity Production: Production of electricity that will offset energy consumption by an annual ~ 30%. The WWTRRF is one of the larger power users in the City. Optimized management of electricity will also allow the City furthered development growth as electricity/grid access is a limiting factor currently. 2. Reduced Chlorine Use: Shade to reduce the degradation of chlorine, thus allowing for less chemical use. This will mean less chemicals in the water and lower operating costs for the plant. 3. Reduced effluent temperature: Shading of the CCC and secondary clarifier that produces lower effluent temperatures which is favorable for the DEQ permit and consequently the health of the McKay Creek and the Umatilla River that are the recipients of the effluent 4. Reduced biogrowth/contaminants in the CCC: Shading of the CCC will reduce the algae growth across the system and minimize ‘debris/contaminants’ entering the system from above. This means less cleaning/maintenance of the CCC which is beneficial for plant optimization and personnel safety. Additionally, less biogrowth/debris means less chlorine usage as well (see item #2 above!).

Address
4300 SW Houtama Rd, Pendleton, OR 97801, USA

Project Status

Completed

Project Milestones

June 2022

City Council authorizes a Professional Service Agreement (PSA) not to exceed $36,750 with AMERESCO and the City Manager to execute the Purchase Order for solar panels.

 

October 2022

Oregon Department of Energy (ODOE) announces an $850,000  Construction Resilience grant for the project

 

August 2023

Pendleton City Council approved the Energy Savings Performance Contract (ESPC) Phase 2 – Design & Construction for the implementation of the WWTRRF Solar Cover Project.

 

Sept. 2025

The City of Pendleton and Ameresco celebrated the ground breaking of the project on Sept. 4, 2024. 

Read more at 

https://pendletonor.gov/publicworks/page/city-ameresco-celebrate-solar-canopy-groundbreaking 

 

January 2025

Footings and catwalk installed. Structure erection expected in March.

 

March 2025

Canopy framing erected to hold solar panels

 

June 2025

On June 11, 2025, the City of Pendleton and Ameresco celebrated the ribbon cutting of the solar canopy. Read more at https://www.businesswire.com/news/home/20250611046090/en/Ameresco-Celebrates-the-Completion-Solar-Canopy-Project-with-the-City-of-Pendleton-Oregon