Solar Battery Storage for WFP

Construction of 100 kilowatt energy storage system at a solar power site near the city Water Filtration Plant . The closed circuit will allow power to flow to the water filtration plant during storm outages and save diesel.
Funding
$816,424 Construction Renewable grant from the ODOE Community Renewable Energy Grant Program
Note:
Project suspended in 2025 due to funding and contractor issues.
| Project Title: | Solar Battery Storage at Buckaroo 1 Solar Array |
| Estimated Construction Cost: | 816,424 |
| Actual Construction Cost: | TBD |
| Project Type: | Facilities |
| Final Project Cost (Construction + Engineering): | TBD |
| Year Completed: | In Progress |
Why It's Needed
This renewable resources will allow power to the water treatment plant during storm outages and save diesel.
Address
1001 Goad Rd, Pendleton, OR 97801, USA
Additional Project Images:

Project Status
In Progress
Project Milestones
Oregon Department of Energy (ODOE) awarded the City of Pendleton a $816,424 Construction Renewable grant to fully fund the project.
City has made initial deposit of 30% of project cost to the contractor for the 100kw battery purchase.
Project suspended due to issues with funding and contractor.