SE 3rd Street Water Line

Installation of 740 linear feet (LF) of 18-inch water main and 640 LF of 12-inch water main on SE 3rd Street from the cul-de-sac north of SE Byers Avenue to SE Frazer Avenue. The new 12-inch water main will connect to two existing 12-inch water mains in the cul-de-sac and extend to SE Byers Avenue and make a connection with a 12-inch water main the City has already installed.
This project also includes:
- New 12-inch water main will be installed between SE Byers Avenue and SE Court Avenue with 12- and 18-inch connections to existing
- New 18-inch water main will be installed between SE Court Avenue and SE Dorion Avenue and between SE Dorion Avenue and SE Emigrant Avenue with 18-inch connections to existing
- Fire hydrant will be replaced at the SE corner of SE Court Avenue.
Project deadline: June 30, 2023
Funding
Urban Renewal District.
| Project Title: | 2022 URD Project - SE 3rd Street Water Line |
| Estimated Construction Cost: | $552,500 |
| Actual Construction Cost: | $643,346 |
| Project Type: | Water |
| Final Project Cost (Construction + Engineering): | TBD |
| Year Completed: | 2023 |
Why It's Needed
This project replaces a 100-year-old water main with a new, more durable equipment with larger water capacity.
Address
SE 3rd St & SE Byers Ave, Pendleton, OR 97801, USA
Project Status
Completed
Project Milestones
Bid awarded to Tapani, Inc. for $643,346.00
Construction work begins on project.
Tests and wrap up begin
Project completed