SE 3rd Street Water Line

Installation of 740 linear feet (LF) of 18-inch water main and 640 LF of 12-inch water main on SE 3rd Street from the cul-de-sac north of SE Byers Avenue to SE Frazer Avenue. The new 12-inch water main will connect to two existing 12-inch water mains in the cul-de-sac and extend to SE Byers Avenue and make a connection with a 12-inch water main the City has already installed.

This project also includes:

  • New 12-inch water main will be installed between SE Byers Avenue and SE Court Avenue with 12- and 18-inch connections to existing
  • New 18-inch water main will be installed between SE Court Avenue and SE Dorion Avenue and between SE Dorion Avenue and SE Emigrant Avenue with 18-inch connections to existing
  • Fire hydrant will be replaced at the SE corner of SE Court Avenue.

Project deadline: June 30, 2023

Funding

Urban Renewal District.

Project Title:2022 URD Project - SE 3rd Street Water Line
Estimated Construction Cost:$552,500
Actual Construction Cost:$643,346
Project Type:Water
Final Project Cost (Construction + Engineering):TBD
Year Completed:2023

Why It's Needed
This project replaces a 100-year-old water main with a new, more durable equipment with larger water capacity.  

Address
SE 3rd St & SE Byers Ave, Pendleton, OR 97801, USA

Project Status

Completed

Project Milestones

October 2022

Bid awarded to Tapani, Inc. for $643,346.00

 

February 2023

Construction work begins on project.

 

April 2023

Tests and wrap up begin

 

May 2023

Project completed