Project Image

The Clearwell baffling curtain system at the Water Filtration Plant (WFP) is designed to create a serpentine pathway for flow through the 1.8 Million Gallon Clearwell. This pathway will allow for more disinfection contact time and help meet a regulatory requirement to produce more water with the new membranes.
Project Title:
Water Filtration Plant (WFP) Clearwell baffling curtain system
Estimated Construction Cost:
TBD
Actual Construction Cost:
TBD
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Why It's Needed
This project helps the WFP remain compliant with new regulations and produces more water with the new membranes.
Address
500 SW Dorion Ave
Pendleton, OR 97801
United States
Project Status
Project Milestones
Project Milestones
Date
October 2023
Milestone Description
Work began under contract with Rotschy on October 23rd
Date
November 2023
Milestone Description
Work completed on Nov. 10, and the WFP was put back into service with the Clearwell the week of November 13th.