West Primary Clarifier Coating

Project Image
photo of primary clarifier and headworks

This project is to protect the West Primary Clarifier from erosion and acid attack that happens in wastewater environments. The launder (outside ring) where the water is moving faster and cascading down a wall is where most of the erosion takes place. Over time this erosion will expose aggregate and, left unchecked, can cause structural failure. The coatings process restores the clarifier by using cementitious grout to fill, smooth and cover any exposed aggregate, a thick epoxy coat to protect the grout from the water and a UV protectant coat to protect the epoxy from the sun.

Funding

Sewer Fund

Project Title:
West Primary Clarifier Coating Contract
Estimated Construction Cost:
TBD
Actual Construction Cost:
$66,819
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Why It's Needed
This is a maintenance project. The Primary Clarifier West was built in 1942, but, with care, could still be in use past 2042.
Address

4300 SW Houtama Road
Pendleton, OR 97801
United States

Project Status

Project Milestones

Project Milestones
Date
August 2023
Milestone Description

City Council approves a Purchase Order to West Primary Clarifier coating contract to Extreme Coatings, Pasco WA, for $66,819.