Project Image

What work is being performed?
- Roadways will be completely reconstructed to address the subgrade failure.
- Catch basins and storm water pipe will be installed to improve and address drainage issues.
- Curb and gutter will be removed and replaced, as needed, to address drainage issues.
- Sidewalks will be removed and replaced, as needed, to address safety issues and to ensure compliance with ADA standards.
- ADA ramps will be installed to meet Federal ADA standards.
2021 Urban Renewal District Street Reconstruction Project
SE Byers Avenue Reconstruction Project – SE 8th Street to SE 12th Street:
1. SE Byers Avenue Reconstruction
2. SE 8th Street Reconstruction
3. SE 12th Street Overlay
Funding
Urban Renewal
Project Title:
2020 URD Street Reconstruction Project
Estimated Construction Cost:
$1,433,694
Actual Construction Cost:
$971,971
Project Type:
Final Project Cost (Construction + Engineering):
$1,049,729
Year Completed:
Address
Intersection of Byers Avenue and SE 12th Street
Pendleton, OR 97801
United States
Project Status
Project Milestones
Project Milestones
Date
June 2020
Milestone Description
Bid awarded to KSH Construction Co., of Bend, for $971,971.00
Address Geolocation