SE 3rd Street Reconstruction

Project Image
Paving on SE Third

This is a planned reconstruction for the 2023 construction season to rebuild the portion of SE 3rd Street from Frazer to Stillman Park, including a new storm drainage system.

  • Roadways will be completely reconstructed to address the subgrade failure.
  • Catch basins and storm water pipe will be installed to improve and address drainage issues.
  • Curb and gutter will be removed and replaced, as needed, to address drainage issues.
  • Sidewalks will be removed and replaced, as needed, to address safety issues and to ensure compliance with ADA standards.
  • ADA ramps will be installed to meet Federal ADA standards.

 

SE 3rd Street may be closed to through traffic on a block by block basis during working hours. SE 3rd Street will need to be reopened with a smooth, flat, passable road surface of gravel or asphalt at the end of the work day for local traffic. Access to driveways and side streets will need to be provided at the end of each work day.

Funding

This project will be funded through Urban Renewal.

Project Title:
SE 3rd Street Reconstruction
Estimated Construction Cost:
$913,750
Actual Construction Cost:
TBD
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Why It's Needed
Overlays and Reconstructions help keep streets usable.
Address

Intersection of SE 3rd St and SE Dorion Ave
Pendleton, OR 97801
United States

Project Status

Project Milestones

Project Milestones
Date
July 2023
Milestone Description

Sealed bids for the 2023 URD Project – SE 3rd Street Reconstruction open. Bids must be received by 2 p.m. Aug. 8, 2023. 

Date
August 2023
Milestone Description

Pendleton City Council approves transfer of up to $104,000 from the water fund to pay the Pendleton Development Commission Contractor for half  the total asphalt cost for the SE 3rd Street Reconstruction Project. The PDC will pay the other half of construction costs.

Date
September 2023
Milestone Description

Work begins on the project

Date
November 2023
Milestone Description

Paving occurred the week of November 13th.  Next steps: Raising of utilities will follow, along with punch list items.  

Date
December 2023
Milestone Description

Project considered complete.