The project completes the Engineering services and Preliminary Design Report. The eventual project would provide:
A new 48” sewer manhole with approximately 15 LF of 18-inch gravity sewer connecting the new manhole and a new sewer lift station. A new packaged sewer lift station with two submersible pumps, each with a capacity of approximately 475 gpm at 74 ft TDH. A new 1,500 LF 6-inch sewer force main exiting the new lift station and feeding into an existing manhole with a gravity sewer main. A new 1,500 LF 8-inch force main running adjacent to the new 6” force main from a new intertie vault to the existing manhole. A new intertie, meter, and valve vault connecting the 6-inch and 8-inch force main and providing valving and metering functionality.
This project completes the design work for this project.
Intersection Airport Road and NW Stage Gulch Road
Pendleton, OR 97801
United States
Project Milestones
MurraySmith submitted 90% design documents
Final design completed