A new sewage lift station (1,375 gpm firm capacity) with triplex submersible pumps located in a precast concrete wet well, a valve vault structure designed as occupied space, and associated pipe, valves, fittings, and site grading.
Funding
The City secured Drinking Water State Revolving Fund loan of $14,855,000 and a Clean Water State Revolving Fund loan of $9,800,000 to assist with water distribution and sewer collection master planning projects. This project is solely a sewer collection system project and adequate CWSRF loan funds are available for this project.
SW 28th Street Lift Station
Pendleton, OR 97801
United States
Project Milestones
Contract awarded to Michael Becker General Contractor, LLC, for the SW 28th Street Lift Station Project in the amount of $1,362,253.00.