The project consists of rebuilding the roadway, replacing damaged curb and gutter and sidewalks, ADA ramps, and storm sewer improvements will also be performed.
This includes:
- Grind and inlay with 2” of asphalt.
- Address ADA ramps to meet Federal ADA standards.
- Remove and replace curb & gutter to improve drainage, address the lack of curb reveal, or repair damaged curbs.
- A few roadways will be completely reconstructed to address the subgrade failure.
2021 Overlay Project List
1 NW 10th Street (NW Despain Ave to NW Furnish Ave)
2 SW 2nd Street (SW Frazer Ave to SW Emigrant Ave)
3 SW 2nd Street (SW Dorion Ave to SW Court Ave)
4 SW Isaac Avenue (SW 12th St to SW 13th St)
5 SW Southgate Place (Cul-de-sac S to ST HWY 395 N INT)
6 SW Ladow Avenue (SW 23rd St to Dead End East)
7 SE Hailey Avenue (SE 6th St to SE 7th St)
8 McKennion Station Road 9 NE 35th Street
Funding
Urban Renewal
Project Title:
2021 City Streets Overlay & Reconstruction
Estimated Construction Cost:
936,073
Actual Construction Cost:
847,844
Project Type:
Final Project Cost (Construction + Engineering):
915,672
Year Completed:
Address
500 SW Dorion Ave
Pendleton, OR 97801
United States
Project Status
Project Milestones
Project Milestones
Date
April 2021
Milestone Description
Bid Awarded to Central Washington Asphalt, Inc. Moses Lake, WA for $847,844.44
Address Geolocation