Cemetery Booster Pump Station

Project Image
generator delivery

This project replaces three existing pumps and adds one additional pump at the Cemetery Water Booster Pump Station. Pumps 1 & 2 will provide 800 gallons per minute (GPM) each with 40 horsepower (HP) motors each and Pumps 3 & 4 will provide 1,500 GPM each with 75 HP motors each.   Installation of new equipment completed in phases during the 2022 construction season.  Water Division will do most of the project work, with electrical wiring and start-up outsourced.

Project completion is expected for May 2023. This is an identified master plan project adopted by City Council June 2, 2015  

Funding

Equipment purchase was funded through Water Fund Capital Outlay

Project Title:
Cemetery Booster Pump Station
Estimated Construction Cost:
TBD
Actual Construction Cost:
$ 70,680
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Why It's Needed
Upgrades to the Cemetery Booster Station will assist with meeting master planning identified issues for peak flow and redundancy (generator) for water system customers located in the Cemetery Pressure Zone. These upgrades will also assist with long-term growth within the Urban Growth Boundary at the west end of the pressure zone and may be eligible for future reimbursement.
Address

9424, 865 Tutuilla Rd
Pendleton, OR 97801
United States

Project Status

Project Milestones

Project Milestones
Date
March 2022
Milestone Description

Bid awarded to Pump Tech LLC for  $70,680  for the purchase and delivery of four pumps to upgrade the Cemetery Water Booster Pump Station.

Date
December 2022
Milestone Description

Water Division crews assembled and installed pump fittings

Date
February 2023
Milestone Description

Pumps, fittings, electrical distribution panels, and variable frequency drives (VFDs) on-site. Generator delivered, and equipment installed. 

Date
September 2023
Milestone Description

Cement pad poured and generator delivered and installed

Date
October 2023
Milestone Description

Cemetery Booster Pump Station (BPS) went offline Oct. 24-25 for installation of new pumps as part of the major upgrade.  Piping and valving was completed to accommodate the major upgrades and the existing natural gas fire flow pump. 

The overall pressure zone Cemetery BPS serves is also served by SE 7th Street BPS, and eventually will be served by the new East End BPS, which means domestic flow and domestic water pressure should be affected by the work. City crews waited to perform this work when our customer demand is low with irrigation season completed.  

The goal is to have all the new equipment installed and begin testing by Thursday, November 2nd.  

Address Geolocation
Additional Project Images: