SE 3rd Street Water Line

Project Image
SE 3rd Water Line

Installation of 740 linear feet (LF) of 18-inch water main and 640 LF of 12-inch water main on SE 3rd Street from the cul-de-sac north of SE Byers Avenue to SE Frazer Avenue. The new 12-inch water main will connect to two existing 12-inch water mains in the cul-de-sac and extend to SE Byers Avenue and make a connection with a 12-inch water main the City has already installed.

This project also includes:

  • New 12-inch water main will be installed between SE Byers Avenue and SE Court Avenue with 12- and 18-inch connections to existing
  • New 18-inch water main will be installed between SE Court Avenue and SE Dorion Avenue and between SE Dorion Avenue and SE Emigrant Avenue with 18-inch connections to existing
  • Fire hydrant will be replaced at the SE corner of SE Court Avenue.

Project deadline: June 30, 2023

Funding

This project is funded through the Urban Renewal District.

Project Title:
2022 URD Project - SE 3rd Street Water Line
Estimated Construction Cost:
$552,500
Actual Construction Cost:
$643,346
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Why It's Needed
This project replaces a 100-year-old water main with a new, more durable equipment with larger water capacity.
Address

Intersection of SE 3rd St and SE Byers Avenue
Pendleton, OR 97801
United States

Project Status

Project Milestones

Project Milestones
Date
October 2022
Milestone Description

Bid awarded to Tapani, Inc. for $643,346.00

Date
February 2023
Milestone Description

Construction work begins on project.

Date
April 2023
Milestone Description

Tests and wrap up begin

Date
May 2023
Milestone Description

Project completed