This project is the first step of constructing a new well at the Wastewater Treatment Resource Recovery Facility. The project includes:
- Drilling and providing for a 24-inch surface casing to a 25-foot depth
- Drilling and providing for a 20-inch casing to a 260-foot depth
- Providing for the 20-inch casing to extend above surface level to a height of 2-feet
- Drilling the remaining 18-inch lower hole to a 400-foot depth
- Providing for an intermediate flow test
- Providing for well development and a pump test of up to 2,400 gallons per minute.
Drilling is one phase of the overall project. City plans to bid a Well House Construction Project in winter2023; with bidding dependent on the drilling phase. The City also plans to pre-purchase motor, discharge head, and bowls based on the pump test results while the well house is under construction
- Well 11B Wellhouse Project: At 90% and has been reviewed by State of Oregon. To be advertised in January / February 2023.
- Well 11B Pumping Equipment: To be solicited after the well is drilled and the pump test performed, tentatively scheduled for late-winter to early-spring.
Funding
This project is being funded through the Federal Safe Drinking Water Revolving Loan Fund, Business Oregon, and local funding.
Project Title:
Well No. 11B Drilling Project
Estimated Construction Cost:
$950,000.
Actual Construction Cost:
782,023
Project Type:
Final Project Cost (Construction + Engineering):
TBD
Year Completed:
Address
4255 S.W. 28th Drive
Pendleton, OR 97801
United States
Additional Links:
Project Status
Project Milestones
Project Milestones
Date
November 2022
Milestone Description
Bid/RFP Due Date
Date
November 2022
Milestone Description
Bid award for Drilling to Holt Services, Milton, WA, in the amount of $782,023.