A book mobile to bring the library to the public. The Pendleton Mobile Library will visit schools, parks, and residential areas in both Pendleton and Mission.
Project Title:
Pendleton Mobile Library
Estimated Construction Cost:
$140,000
Actual Construction Cost:
$140,000
Project Type:
Final Project Cost (Construction + Engineering):
$140,000
Year Completed:
Why It's Needed
To provide access to library services for those who do not live within walking distance of the library or who do not have transportation.
Address
500 SW Dorion Ave
Pendleton, OR 97801
United States
Project Status
Project Milestones
Project Milestones
Date
November 2022
Milestone Description
Mobile Library vehicle delivered and wrapped with decorative design
Date
December 2022
Milestone Description
Shelves and equipment installed
Date
February 2023
Milestone Description
Mobile library completed and stocked with books.