Replaces and rebuilds Byers Avenue from Southeast 7th Street to Main Street, and Southeast 4th Street from Southeast Byers Avenue to Southeast Court Avenue, including pavement and storm drainage, using 2,400 tons of asphalt. This project includes removing and replacing approx. 4,300 feet of curb and gutter, 1,700 yards of sidewalk, 400 yards of concrete driveway approaches, 567 yards of ADA ramps.
Funded through: Urban Renewal
Intersection of SE Byers Avenue and SE 4th Street
Pendleton, OR 97801
United States
Project Milestones
Bid awarded to Humbart Asphalt
Humbart Asphalt begins paving of first lift
Paving work completed. Punch list work continues – raising the manholes from under pavement and installing the manhole lids, then concreting around the manhole lids to street level; locate wire being readjusted in the valve cans; signage installation; and any necessary striping, including stop bar designations.