SE Byers Avenue & SE 4th Street Reconstruction

Project Image
Paving on Byers Avenue

Replaces and rebuilds Byers Avenue from Southeast 7th Street to Main Street, and Southeast 4th Street from Southeast Byers Avenue to Southeast Court Avenue, including pavement and storm drainage, using 2,400 tons of asphalt. This project includes removing and replacing approx. 4,300 feet of curb and gutter, 1,700 yards of sidewalk, 400 yards of concrete driveway approaches, 567 yards of ADA ramps. 

Funded through: Urban Renewal

 

Project Title:
2022 URD Project - SE Byers Avenue & SE 4th Street Reconstruction
Estimated Construction Cost:
$1,704,897
Actual Construction Cost:
$1,588,084
Project Type:
Final Project Cost (Construction + Engineering):
1,715,131
Year Completed:
Why It's Needed
This project uses urban renewal district funds to replacing aging street and infrastructure.
Address

Intersection of SE Byers Avenue and SE 4th Street
Pendleton, OR 97801
United States

Project Status

Project Milestones

Project Milestones
Date
June 2022
Milestone Description

Bid awarded to Humbart Asphalt

Date
October 2022
Milestone Description

Humbart Asphalt begins paving of first lift

Date
February 2023
Milestone Description

Paving work completed.  Punch list work continues –  raising the manholes from under pavement and installing the manhole lids, then concreting around the manhole lids to street level; locate wire being readjusted in the valve cans; signage installation; and any necessary striping, including stop bar designations.