Project Image

This project updates and reconstructs Southwest 10th Street between Southwest Dorion Avenue and Southwest Emigrant Avenue.
During the project, crews will installing storm pipes and three new curb inlet catch basins for storm water; replace 560 tons of asphalt; remove and replace 80 feet of curb and gutter, three utility adjustments, five connections to existing manholes, and three connections to existing storm pipes.
Funded through: Urban Renewal
Project Title:
2022 URD Project - SW 10th Street Reconstruction Project
Estimated Construction Cost:
$349,020
Actual Construction Cost:
$366,478
Project Type:
Final Project Cost (Construction + Engineering):
$388,466
Year Completed:
Why It's Needed
Road and storm line are being reconstructed because of age and condition and to reverse damage of existing storm line.
Address
Intersection SW 10th Street and SW Dorion Ave
Pendleton, OR 97801
United States
Additional Links:
Project Status
Project Milestones
Project Milestones
Date
July 2022
Milestone Description
Pendleton Development Commission approved award to Humber Asphalt for reconstruction of SW 10th. Full contract amount of $339,332 issued
Date
October 2022
Milestone Description
Physical project work begins
Date
November 2022
Milestone Description
Paving Completed