Well No. 11B Drilling Project

This project is the first step of constructing a new well at the Wastewater Treatment Resource Recovery Facility.

The project includes:

  • Drilling and providing for a 24-inch surface casing to a 25-foot depth
  • Drilling and providing for a 20-inch casing to a 260-foot depth
  • Providing for the 20-inch casing to extend above surface level to a height of 2-feet
  • Drilling the remaining 18-inch lower hole to a 400-foot depth
  • Providing for an intermediate flow test
  • Providing for well development and a pump test of up to 2,400 gallons per minute.

Drilling is one phase of the overall project. City plans to bid a Well House Construction Project in winter2023; with bidding dependent on the drilling phase. The City also plans to pre-purchase motor, discharge head, and bowls based on the pump test results while the well house is under construction.

  • Well 11B Wellhouse Project: At 90% and has been reviewed by State of Oregon.  To be advertised in January / February 2023.
  • Well 11B Pumping Equipment: To be solicited after the well is drilled and the pump test performed, tentatively scheduled for late-winter to early-spring. 

Funding

This project is being funded through the Federal Safe Drinking Water Revolving Loan Fund, Business Oregon, and local funding. 

 
Project Title:Well No. 11B Drilling Project
Estimated Construction Cost:$950,000
Actual Construction Cost:$782,023
Project Type:Water
Final Project Cost (Construction + Engineering):TBD
Year Completed:In Progress

Address
4255 SW 28th Dr, Pendleton, OR 97801, USA

Additional Links:

Project Status

In Progress

Project Milestones

November 2022

Bid/RFP Due Date

 

November 2022

Bid award for Drilling to Holt Services, Milton, WA, in the amount of $782,023.