Well 11 & 11B Equipment

City Council awarded construction of Well 11 & Well 11B Wellhouses Project on June 4, 2024. For this project, there are two sets of Owner supplied equipment:

  • Pumping systems for each well
  • Variable frequency drive (VFD) equipment for each well

This equipment was separated from the Wellhouses Project to let staff directly specify the purchase of this equipment for the project. This is an area that staff is more experienced than the consultant that performed the design for the construction. Columbia Electric Supply is the sole-source provider of Rockwell Automation equipment for this region. We direct purchase from them as a sole-source provider.

For our water and wastewater system, we have standardized the use Rockwell Automation equipment, which includes Allen Bradley VFDs, harmonic filters, ethernet kits, telemetry programming, program logic controllers (industrial computers), etc. related to our Supervisory Control and Data Acquisition (SCADA) system. This equipment is necessary to operate and control the motors that will be installed with the pumping systems.

Funding

This project will be funded from the Business Oregon Special Public Works Fund. There is about $10.08 million approved for loan drawdown. Water system rates will cover the debt service associated with this project. This purchase is part of the overall construction costs related to Well 11 & Well 11B Wellhouses Project.

Project Title:Well 11 & 11B owner supplied equipment project
Estimated Construction Cost:$50,000
Actual Construction Cost:$50,101
Project Type:Water
Final Project Cost (Construction + Engineering):$50,101
Year Completed:In Progress

Why It's Needed
This equipment is necessary to operate the new wells 11 and 11B, providing increased water flow for the City of Pendleton.  

Address
4300 SW Houtama Rd, Pendleton, OR 97801, USA

Project Status

In Progress

Project Milestones

July 2024

Pendleton City Council approved a Purchase Order to Columbia Electric Supply for variable frequency drives, harmonic filters, and ethernet kits in the amount of $50,101.18 on July 16, 2024.

June 2024

The Anderson Well, also known as Well 11B, site prep completed. Final electrical equipment arrival estimated to arrive in the end of July

October 2025

Start up and testing complete, final approval from OHA